Into Real Estate and Finance Law ~
December 1996 ~
Significant Changes to Mechanics Lien Statute
The recently enacted amendments to Massachusetts
General Laws Chapter 254 comprise the most significant overhaul of the
Massachusetts Mechanics Lien statute since its enactment in 1915.
Contractors and subcontractors are the primary beneficiaries of the
amendments, which broaden the scope of labor and materials subject to
lien protection, simplify the processes for recording liens and
settling disputes, and generally increase the likelihood of prompt
payment to contractors. Developers and lenders must revise their
current procedures for processing contractor payments in order to
comply with the new law. Construction lenders will be particularly
affected by the new provision of the statute which requires that the
lender continue to make loan advances after the recording of a Notice
of Contract by a general contractor (though not if filed by a
subcontractor).
The effective date of the amendments is November 7,
1996; however, because the amendments are effective for construction
projects for which a first mortgage or Notice of Contract is recorded
on or after February 7, 1997, the real effects of the changes will not
be apparent until February 7, 1997.
This newsletter highlights a few of the significant
changes in the law and identifies ways in which lenders' and
developers' practices will need to be modified.
Expansion of Scope of Statute
The revised Mechanics Lien Statute extends
mechanics lien protection to a broader range of persons providing
labor and materials. In particular, the statute now grants statutory
rights to:
- parties involved in the erection, alteration,
repair or removal of a building, structure or other improvement
to real property;
- parties furnishing material or rental
equipment, appliances or equipment;
- and parties providing construction
management and general contractor services
Under the revised statute, a mechanics lien can
attach to a less-than-fee property interest of a contracting party
(e.g., a leasehold interest), unlike the prior version of the statute
which required the contracting party to be the "owner of land"
on which the lien was to attach. In addition, it is no longer
necessary that the lien relate to work on a building or structure,
thus granting lien rights to site work contractors such as
landscapers, parking lot surfacers and utility contractors.
Differences Impacting General Contractors' Lien Protection
To perfect a mechanics lien under the pre-1996
statute, a contractor was required to record a Notice of Contract with
the Registry of Deeds for the county (or district) in which the
subject property was located on or before the completion date stated
in the construction contract. To address the difficulties associated
with identifying a precise completion date (frequently a moving
target), the deadline for recording the Notice of Contract under the
amended statute is now measured from the more practical date of a
project's "substantial completion."
Specifically, a Notice of Contract must be filed
before the earliest to occur of:
- 60 days after the recording of a Notice of
Substantial Completion in the new statutory form executed by the
project owner and the general contractor;
- 90 days after the recording of a Notice of
Termination (if the contract is terminated before completion) in
the new statutory form, executed by the project owner; or
- 90 days after the last of the labor and
materials has been furnished by the general contractor (or anyone
claiming through the general contractor).
To enforce its lien rights, the contractor must
also file a Statement of Account, commence a civil action and record a
copy of the complaint for such action before specified deadlines
stated in the revised statute.
Differences Impacting Subcontractors' Lien Protection
The revised statute also creates new procedures
which subcontractors must follow to perfect their mechanics liens. In
addition to following the procedures applicable to contractors to
perfect their liens, a subcontractor must also (a) include a brief
accounting of its claim in the recorded Notice of Contract, and (b)
serve a copy of the Notice of Contract on the project owner by
certified mail. If the subcontractor does not have a direct
contractual relationship with the general contractor, it must also
provide the general contractor with a Notice of Identification
in the new statutory form within 30 days of commencement of the
subcontractor's work on the project to put the general contractor on
notice to provide the subcontractor with a copy of the Notice of
Substantial Completion.
Differences Impacting Construction Lenders
Under the pre-1996 statute, construction lenders
commonly refused to advance construction loan advances upon the
recording of a Notice of Contract because lenders lost their priority
position to the amount of unpaid requisitions for work done through
that date for all loan advances made after the date of recording of
the Notice of Contract. This applied to both Section 2 liens (general
contractors) and Section 4 liens (subcontractors). The revised statute
prohibits a lender from refusing to advance construction proceeds
solely because a general contractor has filed a Notice of Contract,
provided that the general contractor submits a statutory form of Partial
Payment Waiver and Subordination Form to the lender with each
partial payment requisition. By submitting the Waiver Form, the
general contractor subordinates its mechanics lien to the lender's
mortgage interests for all amounts previously received by the
contractor, thus addressing many of the lender's priority concerns;
however, the contractor is not required to subordinate its priority to
any earned but unpaid retainage to which the contractor is entitled.
The revised statute also penalizes lenders for slow payment of
requisitions: if the lender fails to disburse funds within 25 days
after the last day of the payment period subject to the waiver, then
the contractor will have a prior lien over subsequently disbursed loan
funds for all work performed after the last day of the payment period
stated in the waiver. As a result, construction lenders must re-work
the construction loan requisition provisions of their loan documents
and the requisition processing procedures in order to address these
changes in the law. Lenders may also require more stringent bonding
requirements if the project can support the cost of such bonds.
Change in Scope of Personal Labor Lien
Under the pre-1996 statute, a contractor or
subcontractor providing services without a written contract could
claim a mechanics lien for up to 18 days work during the 40 days
preceding the recording of a Statement of Account with the Registry of
Deeds. Under the revised statute, the lienholder can make a claim for
up to 30 days work during the 90 days preceding recording. Lenders
must revise their forms of Mechanics Lien Affidavits to reflect this
change in the law.
Conclusion
Discussion regarding the overhaul of Chapter 254
has taken place over much of the past decade. Given the ambiguities of
the lien law prior to the 1996 amendments, most of which worked
against the construction industry, it was probably inevitable that
significant changes benefitting that industry would occur. Under the
former statute, contractors, fearful of disrupting the construction
process or upsetting developers and their lenders, would often wait to
pursue their statutory mechanics lien rights until all other means of
resolving payment issues proved unsuccessful, frequently resulting in
strained relationships and forfeited liens. Under the revised statute,
contractors should be able to resolve their differences with
developers in a much less confrontational manner, and get paid much
earlier on in the process. Thus, lenders and developers, as well as
contractors and subcontractors, will benefit from the greater
certainty which the revised statute brings to the process of resolving
contract payment disputes.
Published by The Banking, Finance and Real
Estate Section of Peabody & Arnold's Business Law Group
© 1996, 1997 Peabody & Arnold 50
ROWES WHARF·BOSTON, MA·PHONE 617·951·2100·FAX
617·951·2125 ONE CITIZENS PLAZA·PROVIDENCE, RI·PHONE
401·831·8330·FAX 401·831·8359 ONE CITY
CENTER·PORTLAND, ME·PHONE 207·773·6300·FAX 207·773·0609
This publication is intended for general
information purposes only; it does not constitute legal advice. For
legal issues that arise, the reader should consult legal counsel. This
document may be considered "advertising" under Massachusetts
Supreme Judicial Court Rule 3:07. |